Havre des Pas Resurfacing work has resumed.
It was suspended last week because technical issues at the Ronez manufacturing plant meant asphalt couldn't be supplied.
Work that didn't need asphalt has continued since.
A government spokesperson says, as things stand, the project should finish before the end of this month as scheduled.
The work started on 10 January.

Concerns were raised in the last States sitting about the disruption this work was causing.
Infrastructure Minister Deputy Kevin Lewis said the work was planned in the early months of the year as traffic figures demonstrated that it was the quietest period for the road network and have the least impact on the bus network.


4.7% increase in Jersey old age pension
'No final decision' on planned Apple Crusher relocation
DFDS Christmas timetable signed off... but still not published
Opening of 'transformed' Departure Lounge weeks away
Should the King Street apple crusher be relocated?
Jersey Bulls restore away match livestream
Jersey population stable but ageing as migration falls
Ministers meet to discuss Channel Islands connectivity