Wednesday teatime, 10 January at 17.50, demand reached 94.2MW which equals the amount of electricity being drawn during another cold spell in 2021.
Guernsey Electricity can take a maximum of 60MW from the undersea cable link with France.
This means the North Side power station was used heavily this week, particularly on Wednesday, as this graph shows.

Demand caused some outages in the Vale and Castel areas and Jon Sexton, head of engineering and design at the States owned company, said there were other glitches:
"The additional demand on the electricity network caused some localised supply interruptions and other minor issues, such as lights dimming or minor display errors on appliances. The company’s engineering teams responded to any issues as they occurred and any inconvenience caused is regretted."
“As more Islanders explore options such as electric heating or electric vehicles, such demand is forecast to rise in the future.”


Guernsey Waste improves the quality of its free garden compost
Guernsey cat lover to ride the length of Britain in nine days
Unclaimed CI Co-op cash funds community projects
Work to commence on 70 affordable flats and homes in Guernsey
A new tax, more 'proportionate' to wealth, to be put to Guernsey's States
Guernsey gives £75k for Islands Unlimited inter-islands sailings
Guernsey tax package to raise more States income but protect low earners
Changes to make Guernsey's buses more reliable